Activity | Duration(days) | Precedence | Cost/day(RS.) |
A | 8 | 200 | |
B | 4 | 200 | |
C | 4 | A,B | 300 |
D | 4 | B | 400 |
The progress after the end of 12th day is as follows:
Activity | %Completion | Incurred Cost |
A | 100 | 1400 |
B | 100 | 400 |
C | 75 | 1000 |
D | 50 | 1000 |
Calculate SV, SPI, CV, and CPI respectively.