Perform Earned value analysis of the given project.

Activity Duration(days) Precedence Cost day(Rs) Total Cost
A 5 _ 200 1000
B 5 A 200 1000
C 10 A 100 1000
D 5 A, B 200 1000

The progress after the end of 10th day is as follows:

Activity %completion Incurred Cost
A 100 1200
B 100 800
C 40 800
D 0 0

Calculate SV, SPI, CV and CPI respectively.