| Activity | Duration (days) | Precedence | Cost/day (Rs.) |
| A | 3 | 500 | |
| B | 3 | A | 100 |
| C | 4 | B | 400 |
| D | 2 | B | 500 |
| E | 3 | D | 500 |
The progress after the end of 8th day is as follows:
| Activity | % completion | Incurred Cost |
| A | 100 | 2000 |
| B | 100 | 500 |
| C | 25 | 500 |
| D | 50 | 500 |
| E | 0 | 0 |
Calculate SV, SPI, CV, and CPI respectively.