| Activity | Dyration(days) | Precedence | Cost/day (Rs.) |
| A | 6 | 100 | |
| B | 6 | A | 100 |
| C | 8 | B | 200 |
| D | 4 | B | 300 |
The progress after the end of 16th day is as follows:
| Activity | % completation | Incurred Cost |
| A | 100 | 800 |
| B | 100 | 400 |
| C | 25 | 500 |
| D | 50 | 400 |
Calculate SV, SPI. CV and CPI respectively.