HamroCSIT Logo
HAMRO CSIT
  • Course New
  • Entrance
    • Take Free Test
    • MCQ Questions
    • Colleges
    • Entrance Class
    • Entrance Books
    • Free Entrance Video Course
  • Semester
    • First Semester
    • Second Semester
    • Third Semester
    • Fourth Semester
    • Fifth Semester
    • Sixth Semester
    • Seventh Semester
    • Eight Semester
  • Questions
  • Subscription Automated
  • Notices
  • Articles
  • More
    • Ask Question
    • College Ambassadors
    • Financial Support Program
    • Contribute
    • Contact Us
Login Register
Hamro CSIT User Account
  • Sign In
  • Create Account




Shape | Hamro CSIT Shape | Hamro CSIT Shape | Hamro CSIT Shape | Hamro CSIT
Subject

Software Project Management

This course familiarizes students with different concepts of software project management mainly focusing on project analysis, scheduling, resource allocation, risk analysis, monitoring, control and software configuration management.

Subject Image | Hamro CSIT
  • Chapters
  • Syllabus
  • Question Banks
  • Questions
  • Text Book
  • Practical
  • Viva

Exam Year

  • SPM Question Bank 2082
  • SPM Question Bank 2081
  • SPM Question Bank 2080
  • Software Project Management 2079
  • Software Project Management 2078

Tribhuvan University

Institute of Science and Technology

2078

Bachelor Level / elective-iii-semester / Science

Computer Science and Information Technology( CSC415 )

Software Project Management

Full Marks: 60+20+20

Pass Marks: 24 +8+8

Time: 3 Hours

Candidates are required to give their answers in their own words as far as practicable.

The figures in the margin indicate full marks.

Section A

Attempt any Two questions.

1

Perform earned value analysis of the following project

Activity Duration(days) Precedence Cost/day(RS.)
A 8 200
B 4 200
C 4 A,B 300
D 4 B 400

The progress after the end of 12th day is as follows:

Activity %Completion Incurred Cost
A 100 1400
B 100 400
C 75 1000
D 50 1000

Calculate SV, SPI, CV, and CPI respectively.

2

Differentiate between programme management and portfolio management. Define Payback period. How can it be used as an evaluation technique? What are its advantages and disadvantages?

3

Suppose you have been assigned to develop online voting system. List four risks that might affect the success of the system. Rank the risks based on Risk exposure. Develop contingency plan for the highest ranked risk.

Section B

Attempt Any Eight Questions

4

Calculate ROI for the following project

Year Project
0 -50000
1 5,000
2 5,000
3 20,000
4 40,000
5 50,000
5

Differentiate between activity-based approach and hybrid-based approach for identifying activities.

6

Why software project management is a challenging activity?

7

Draw  precedence network diagram for the following and identify the critical path.

Activity Duration(Weeks) Precedence
A 5
B 3 A
C 5 A
D 10 B, C
8

Explain Maslow’s hierarchy of needs.

9

Briefly explain different quality factors.

10

Explain the process of Software Configuration Management.

11

Differentiate between Gantt chart and slip chart.

12

Short Notes

1. Present worth

2. PERT diagram

Software Project Management Question Bank Solution 2078
Solution Video
Solution
Share

Share this link via

Or copy link

logoHAMROCSIT

Hamro CSIT is a comprehensive web and mobile platform that provides B.Sc. CSIT students with resources like notes, syllabi, question banks, solved past papers, practical files, and free entrance preparation materials — all in one place.

  • [email protected]
Semester
  • First Semester
  • Second Semester
  • Third Semester
  • Fourth Semester
  • Fifth Semester
  • Sixth Semester
  • Seventh Semester
  • Eighth Semester
Links
  • About Us
  • FAQs
  • Sitemap
  • Privacy Policy
  • Terms and Conditions
  • College Ambassadors
  • Financial Support Program
Hits Counter
20091078
Google Play App Store
Follow Us

Copyright 2026 | HAMROCSIT | All Right Reserved

Official Payment Partner Esewa Logo
HAMROCSIT.COM

Copyright 2024 | HAMROCSIT.COM | All Right Reserved - Nymna Technology